Notice of Lane Closure – Hunt Club Rail Bridge

As part of the Stage 2 O-Train  South Extension Project, construction of the Hunt Club Rail-over-Road Bridge is underway. The bridge is a major part of the infrastructure advancement project for the O-Train South Extension and once complete, it will not only serve to improve the rail link to communities in South Keys and surrounding neighbourhoods, but will also provide a new North / South, Multi-Use Pathway connection for residents.

What

Geotechnical monitoring is required to be completed in the westbound left lane of Hunt Club road, between the Transitway overpass and the Airport Parkway.

When

Work will take place from 9:30 to 10:30 am on March 4, 5, 8, 10, 12, 16, 18, 22, 24 and 26, pending inclement weather and schedule changes.

Why

To conduct geotechnical monitoring at the work site.

Where

In the westbound left lane of Hunt Club road, between the Transitway overpass and the Airport Parkway.

Work area shown in red.

Anticipated Impacts

  • Westbound traffic on Hunt Club Road will share the right lane around the work area for the duration of the closure. Traffic control measures will be in place.
  • Cycle lanes on both sides of Hunt Club Road through the work site will remain closed for the duration of this work due to increased truck traffic and heavy construction equipment. Cyclists will be required to adhere to signage and share the lane with other traffic.

If you have questions about this work, please contact the City’s representative:

Michael Brossoit
Stakeholder Relations, Rail Construction Program
City of Ottawa
Email: michael.brossoit@ottawa.ca
Website: ottawa.ca/stage2

Notice of Night Work – Hunt Club Rail Bridge

We received a notice from Councillor Brockington that construction of the Hunt Club Rail-over-Road Bridge as part of the Stage 2 O-Train Trillium Line South Extension Project is ready to proceed.  This will involve night work over the next few weeks, planned to be completed by February 24, 2021.

Work is being conducted at night to reduce impacts to vehicular traffic, including emergency vehicles. To maintain safety, cycle lanes on both sides of Hunt Club Road through the work zone will remain closed for the duration of this work due to increased truck traffic and the presence of heavy construction equipment. Cyclists and pedestrians will be required to adhere to signage.

Work will be conducted every night pending inclement weather and schedule changes. The utmost consideration for residents’ well-being has been considered in planning this activity and everyone involved is committed to this project advancing smoothly and with respect for everyone’s comfort and safety.

Anticipated Impacts:

  • Cycle lanes on both sides of Hunt Club Road through the work site will remain closed for the duration of this work due to increased truck traffic and heavy construction equipment. Cyclists will be required to adhere to signage and share the lane with other traffic.
  • Although construction noise is not expected to exceed 85 decibels at the site of activity, reducing to 56 decibels at 30 metres from the site, the public will experience noise and some vibration associated with construction activity. Efforts will be made to avoid directing light toward residences.

Further information is available at the following link:
Stage 2 Trillium Line South Extension – Overnight Construction on Hunt Club Rail Bridge
(Note the schedule on the link may not reflect the latest update with Feb 24th completion.)